In 2025, we will keep working on the citys bridges and quays. We will make replacements and renovations, and restrict heavy traffic where necessary. What is coming up this year?
After 5 years, we are still conducting our major approach to the bridges and quays.
Ongoing Projects
This year, we will focus on 772 meters of quay wall and 2 bridges. We aim to complete the Nieuwe Herengracht by May, with the remaining quay walls later this year. This concerns the last parts of Jacob Catskade and other locations. We also expect to finish replacements after the summer.
New Projects
This year, we will start 2 kilometers of quay wall and 4 bridges. These include various quays in the city, where we will replace foundations and renovate them.
Repairs and Safety Measures
Some quays in poor condition are waiting for repairs. We temporarily fix them and set weight limits at the most vulnerable places to avoid further damage.
The Future
We are investigating sustainable solutions such as heat pumps behind the quays and how to better care for trees. Amsterdam is working on safe and future-proof bridges.