New integrated child center in Sint Nicolaasga: construction starts summer 2026
Residents of Sint Nicolaasga can expect a new Integrated Child Center (IKC) by summer 2026. The project includes temporary relocation of local school and daycare services, followed by demolition of the old building. Stay informed about construction timelines and safety measures.
| Key Data Point | Details |
|---|---|
| Project | New construction of IKC Sint Nicolaasga |
| Main Contractor | Bouwbedrijf Van der Meer (Sneek) |
| Installations Contractor | P. de Vries Installatietechnieken (Leeuwarden) |
| Temporary Relocation | Primary school De Paedwizer and daycare (April 13-26, 2026) |
| Demolition Start | Week 18 (April 27 - May 3, 2026) |
| Construction Start | Before summer vacation 2026 |
| Information Meeting | May 2026 (details on schedule, access routes, and safety) |
| Permit Inspection | Public inspection for six weeks after permit issuance |
The municipality of De Fryske Marren is responsible for the development and maintenance of educational facilities within its region. This project ensures that local children and families have access to modern, integrated childcare and educational services.
No ☕ no Openrijk
A lot of hard work happens behind the scenes. Good coffee is more than welcome :)
Read the full translated article below
New construction of IKC Sint Nicolaasga
The board has decided which contractors will carry out the new construction of the IKC in Sint Nicolaasga. The building will be constructed by Bouwbedrijf Van der Meer from Sneek. The installations, such as heating and electrical systems, will be handled by P. de Vries Installatietechnieken from Leeuwarden.
Before construction can begin, the environmental permit must first be issued. After that, this permit will be available for public inspection for six weeks. If everything proceeds according to plan, the contractor will start construction before the summer vacation of 2026.
Temporary accommodation and demolition
Work is underway to arrange temporary accommodation for primary school De Paedwizer and the daycare center. They are expected to move in week 16 and 17 (April 13 to April 26, 2026). After that, the current school building of De Paedwizer can be demolished. Demolition is expected to start in week 18 (April 27 to May 3, 2026).
Information meeting in May
In May 2026, the contractor will organize an information meeting. Residents and other interested parties will then receive more information about the construction schedule, access routes, and safety around the construction site.