Nijmegen's High Street undergoes major redesign: road closures and bus detours in April
Nijmegen's High Street will partially close from 7 to 24 April for a redesign, affecting traffic and bus routes. The project aims to enhance greenery, safety, and aesthetics in the Valkhofkwartier, but expect disruptions to daily commutes and local business access.
| Detail | Information |
|---|---|
| Location | High Street, Nijmegen (Gelderland) |
| Closure Dates | 7–24 April 2024 |
| Phased Closures | Phase A: 7–15 April (inner bend), Phase B: 15–24 April (outer bend) |
| Overnight Closure | Voerweg (1–2 April, 22:00–06:00) |
| Affected Bus Line | Line 8 (stops temporarily out of service: Kronenburgersingel, Waalkade, etc.) |
| Alternative Bus Stops | Near Nijmegen Station, Centrum Zuid, Prins Hendrikstraat |
| Project Goals | Green central reservation, new zebra crossing, fountain, and park renovations |
| More Info | Mijn Wijkplan Valkhofkwartier |
The Municipality of Nijmegen is responsible for urban infrastructure projects, including road redesigns and public space improvements. This initiative aims to enhance safety, accessibility, and livability in the Valkhofkwartier, aligning with broader city planning goals.
Openrijk is free and ad-free
Do you value our work? Help us stay online with a small contribution.
Read the full translated article below
High Street temporarily closed in April for road redesign
The High Street in Nijmegen will be partially closed from 7 to 24 April. The closure is necessary for the redesign of the bend, which includes the installation of a green central reservation and a new zebra crossing. The Voerweg will also be closed on the night of 1 to 2 April.
Phased closure
The work will be carried out in two phases:
- Phase A: 7 to 15 April – The inner bend will be closed. Traffic will still be possible in one direction: from Hertogstraat to Voerweg.
- Phase B: 15 to 24 April – The outer bend will be closed. Traffic will again be possible in one direction: from Hertogstraat to Voerweg. Traffic from Burchtstraat can exit the city centre via a temporary route. Separate supply routes have been set up for businesses.
Public transport
Bus line 8 will operate an adapted route during the works. Several stops, such as Kronenburgersingel, Waalkade, Voerweg and Hertogplein, will temporarily be out of service. Passengers can use alternative stops near Nijmegen Station, Centrum Zuid and Prins Hendrikstraat. Other bus lines will remain unchanged.
Overnight closure of Voerweg
On the night of Wednesday 1 to Thursday 2 April, the Voerweg will be temporarily closed between 22:00 and 06:00. This is necessary for the installation of a manhole for the new fountain at Kelfkensbos.
Improvements to Valkhofkwartier
The works are part of the redesign of Kelfkensbos and the Valkhofkwartier. The area will feature more greenery, new paving, art and a water feature. The Valkhof Museum and the park will also be renovated.