Major lock renovation in Zuid-Willemsvaart starts March 30: expect delays and closures
From March 30, Lock 13 near Someren will close for renovations, causing disruptions for shipping and road traffic until June 19. Cyclists and drivers should prepare for detours and delays, especially on key dates in April and June.
| Key Detail | Information |
|---|---|
| Location | Lock 13, Zuid-Willemsvaart canal near Someren, Noord-Brabant |
| Duration of Renovation | March 30, 2026 – June 19, 2026 |
| Impact on Shipping | Lock completely closed |
| Key Closure Dates | April 9 (bridge closed to all), April 17 (bridge closed to motorized traffic) |
| Detour Impact | Approx. 10 minutes additional travel time |
| Project Part | Tilburg 3 project |
| Lock Gates Lifespan Post-Renov. | 15 years |
Rijkswaterstaat is responsible for the management and maintenance of major waterways and infrastructure in the Netherlands, including locks like Lock 13. This renovation is part of their broader efforts to ensure safe and efficient waterborne and road traffic.
Refueling time ☕
Openrijk navigates piles of government news daily. Your coffee helps us stay on course.
Read the full translated article below
Starting Monday, March 30: Renovation work begins on Lock 13
Rijkswaterstaat will begin renovations on Lock 13 in the Zuid-Willemsvaart canal near Someren on Monday, March 30, 2026. The work will continue until June 19, 2026. During this period, the lock will be completely closed to shipping, and road traffic will experience delays on certain days. The renovation is part of the Tilburg 3 project.
As part of the renovation, the lock gates and pivot points will be replaced. To minimize disruption as much as possible, the construction site will be set up on the lock premises.
Closures and traffic delays
- April 9: Bridge closed to cyclists and motorized traffic (detour in place).
- April 17: Bridge closed to motorized traffic; cyclists may pass under supervision.
- June 3: Cars and (moped) cyclists may pass under supervision.
- June 15: Cars and (moped) cyclists may pass under supervision.
When the bridge is inaccessible, a local detour will be in effect. Allow for approximately 10 minutes of additional travel time.
Rijkswaterstaat will temporarily deploy additional barriers to enable faster and safer work. After the renovation, the lock gates will last approximately 15 years.
More information
For more information about the project, visit www.rijkswaterstaat.nl/tilburg3