Upgrades to Beegden and Panheel roads start next week: safer routes and detours in place
Starting 30 March, Heerstraat Zuid in Beegden and Heelderweg in Panheel will undergo major upgrades to improve traffic safety and flow. Expect detours, reduced speed limits, and temporary bus stop changes for about four weeks.
| Key Detail | Information |
|---|---|
| Roads affected | Heerstraat Zuid (Beegden), Heelderweg (Panheel) |
| Start date | 30 March 2026 |
| Duration | Approximately 4 weeks |
| Contractor | Asfaltbouw |
| Key changes | Two lanes, wider central reservation, speed measures (60 km/h limit) |
| Detours | Beegden-Heel: Kastanjelaan & Nieuwstraat; Panheel-Heel: Schutteheide, Napoleonsbaan |
| Bus stop changes | Temporary rerouting via Mgr. Savelbergweg and Polderweg |
| Additional maintenance | 1,800 m² asphalt renewal, new bridge wearing course |
| Contact for questions | J. Erdmann, 0475 – 85 25 00 or j.erdmann@gemeentemaasgouw.nl |
The Municipality of Maasgouw is responsible for maintaining local infrastructure, ensuring roads meet safety standards and remain accessible for residents and businesses. These upgrades reflect their commitment to improving traffic flow and reducing accident risks in the region.