Beilen's Esweg set for major upgrade: safer roads and modern sewers coming soon
Residents of Beilen can expect significant improvements as the renovation of Esweg, Linthorst Homanweg, and Asserweg begins. The project promises safer roads, modern sewer systems, and better accessibility, though some traffic disruptions are expected.
| Key Data Point | Details |
|---|---|
| Project Start Date | April 13, 2026 |
| Streets Involved | Esweg, Linthorst Homanweg, Asserweg |
| Contractor | Avitec (Nieuw-Buinen) |
| Project Duration | April 2026 - 2027 |
| Key Improvements | New separate sewer system, road resurfacing, sidewalk and bike path redesign |
| Traffic Impact | Esweg closed to through traffic; residences and businesses remain accessible |
| Contact for Residents | Avitec’s environmental manager via ‘News from the Construction’ app |
| Alderman | Jan Schipper |
The municipality of Midden-Drenthe is responsible for maintaining and upgrading local infrastructure, ensuring safe and sustainable roads and utilities for its residents. This project reflects their commitment to improving living conditions and future-proofing essential routes in Beilen.
Coffee for reading ☕
Openrijk brings government news together in one place, free and without ads.
But it does need coffee to keep it that way :)
Read the full translated article below
Alderman Jan Schipper gives the starting signal for the renovation of Esweg in Beilen
March 4, 2026 - Alderman Jan Schipper today (March 4) officially gave the starting signal for the renovation of Esweg, Linthorst Homanweg, and Asserweg. With the unveiling of a construction board and the symbolic 'flipping' of the first tile at Esweg, the works can officially begin. The municipality and contractor Avitec are thus taking the step towards a safer and future-proof route through Beilen.
“We have prepared this project together with the neighborhood,” according to alderman Jan Schipper. “I am pleased that the shovel is now really going into the ground. We are not only renewing the road surface but also thoroughly tackling the sewer system. This way, we are preparing the street for the future and ensuring a more pleasant living environment.
Construction starts on April 13
While the preparatory works, such as the removal of trees, have been carried out over the past week, the first real shovel will go into the ground for the construction works on Monday, April 13, 2026. From that date, Esweg will be closed to through traffic. However, residences and businesses on Esweg will remain accessible by car during the works.
What will happen?
The works, which will be carried out by contractor Avitec from Nieuw-Buinen, include, among other things, the replacement of the existing sewer by a separate system for rainwater and wastewater. After the sewer work, utility companies will start working on cables and pipes. As the final step, the road, sidewalk, and bike path will be completely redesigned with new paving.
Planning and phasing
- Phase 1 (April through June 2026): Start of the sewer works.
- Phase 2 (June through September 2026): Continuation of sewer work.
- Phase 3 (August through December 2026): Completion of sewer work and start of the redesign for this part.
- Follow-up (2027): In the new year, the sewer work on Asserweg will start, and the final redesign of the other phases will take place.
After the sewer work, temporary asphalt will be applied each time so that the road is quickly safe to use for residents before the final paving is laid.
Direct contact and information
Residents can contact the environmental manager of Avitec for questions about the day-to-day operations. The most up-to-date planning and information about accessibility can be followed by everyone via the app ‘News from the Construction’ or via this website.