Roadworks in Drachten: Postlaan and Biskopswei closed for maintenance from 30 March
Residents and businesses in Drachten face temporary road closures as the municipality carries out essential maintenance on Postlaan and Biskopswei from 30 March to 5 June. Expect detours and delays, with some properties inaccessible during working hours.
| Detail | Information |
|---|---|
| Location | Postlaan and Biskopswei, Drachten (Fryslân) |
| Duration | 30 March – 5 June 2026 |
| Phases |
- 30 March – 10 April: Biskopswei (De Trisken – Broekfinne)
- 13 April – 1 May: Biskopswei/Postlaan (Broekfinne – Buitensvallaat, including bridge)
- 4 May – 5 June: Postlaan (Buitensvallaat – Lauwers) | | Closures | Temporary closures for through traffic; properties inaccessible on asphalt days | | Detours | Via yellow signs; cycle paths remain open | | Contact | Municipality of Smallingerland: 0512 58 12 34 |
The municipality of Smallingerland is responsible for maintaining local infrastructure, including roads and bridges, to ensure safety and accessibility for residents and businesses. These works are part of routine upkeep to prevent long-term disruptions and hazards.
Happy with Openrijk?
Then support us with a small contribution
external link to whydonate.comRead the full translated article below
Maintenance on Postlaan and Biskopswei: temporary closures from 30 March
The municipality of Smallingerland will carry out maintenance on Postlaan and Biskopswei in Drachten from Monday 30 March to Friday 5 June. During these works, parts of the road will be temporarily closed to through traffic.
Work carried out in phases
To maintain accessibility for residents and businesses as much as possible, the work will be carried out in several phases:
- Weeks 14 and 15 (30 March – 10 April): Biskopswei (De Trisken – Broekfinne)
- Weeks 16 to 18 (13 April – 1 May): Biskopswei / Postlaan (Broekfinne – Buitensvallaat, including bridge)
- Weeks 19 to 23 (4 May – 5 June): Postlaan (Buitensvallaat – Lauwers)
Expect detours
During the works, the following measures will apply:
- Through traffic will be diverted via yellow signs
- Cycle paths will remain accessible
- Emergency services have been informed
- Allow extra travel time
Temporarily less accessible
On specific days when asphalt is milled or laid, properties along the road will be temporarily inaccessible between 07:00 and 16:30. The road will also remain closed after working hours.
Have you scheduled transport on these days? We advise you to plan it outside working hours.
Planning dependent on weather
The works depend on weather conditions. As a result, the planning may change. The municipality and contractor will do everything possible to minimise inconvenience.
Questions?
For general questions, you can contact the municipality of Smallingerland by calling 0512 58 12 34.