Vlieland marina upgrade starts October 2026: what boat owners need to know
Vlieland’s marina is set for essential safety upgrades starting October 2026, with partial closures expected. The project aims to secure the harbour for decades while minimising disruption to residents and boat owners during the off-season.
| Key Detail | Information |
|---|---|
| Location | Vlieland marina, Netherlands |
| Start Date | 1 October 2026 |
| Contractor | Gebr. Van ’t Hek |
| Closure Area | From helipad to harbour office |
| Duration | Outside boating season; exact dates TBA |
| Technical Process | Sheet piling replacement, slope stone removal, and reinstatement |
| Stakeholders | Municipality of Vlieland, TAUW, Vlieland Marina Foundation (SAV) |
The Municipality of Vlieland is responsible for maintaining local infrastructure, including the marina, to ensure safety and accessibility for residents and visitors. This project reflects its duty to uphold public works standards and collaborate with engineering firms and contractors.
Openrijk has no cookies or ads
But could use some support
external link to whydonate.comRead the full translated article below
Update on the restoration of the marina
The sheet piling of the marina requires replacement. This is necessary to ensure the safety of the harbour and the surrounding land. Over the past few months, the Municipality of Vlieland, in collaboration with consultancy and engineering firm TAUW, has been working hard on preparations for these works.
Where do we stand now?
The initial investigations have been completed, including those into the soundings in the harbour. A contractor has also been selected: Gebr. Van ’t Hek has won the tender. Collaboration has begun, and the first construction team meetings have taken place. In the coming weeks, the municipality, TAUW, and Gebr. Van ’t Hek will work together with the Vlieland Marina Foundation (SAV) to finalise the implementation plans.
What will the works entail?
The works will be carried out from land using two pile-driving rigs. This means that no large floating equipment will be required in the marina itself. From 1 October 2026, part of the harbour will be closed, from the helipad to the harbour office. This schedule will be closely coordinated with the harbour master and other stakeholders to ensure the harbour remains as accessible as possible.
Once the plans are finalised, residents and boat owners will be informed of the exact implementation dates and any temporary disruptions.
What does the technical process involve?
In brief: during the works, the stones on the slope will be temporarily removed. The new sheet piling will then be installed, while the existing sheet piling is gradually loosened and removed. Once the new sheet piling is secure, the paving and slope stones will be reinstated. This will restore the harbour to a safe and future-proof condition.
What does this mean for residents and boat owners?
The works are scheduled outside the boating season, minimising disruption as much as possible. While some temporary inconvenience may occur, phased working and close coordination with stakeholders should help to keep this to a minimum.
Looking ahead
With this approach, the municipality, TAUW, and Gebr. Van ’t Hek are working step by step towards a safe marina that will serve for decades to come. We will continue to keep residents and harbour users regularly informed about progress.
