On May 26, work will begin at the Gooiseweg - Ganzenweg intersection. The waiting lanes towards Harderwijk will be extended and partly doubled. This gives waiting traffic more space, improves flow, and reduces traffic jams. From February, the subsoil near the Zeewolde - Harderwijk exit will be reinforced. During this work, a lower speed limit applies and traffic disruptions may occur.
What will change?
- Traffic from Zeewolde to Harderwijk: the right-turn waiting lane will be longer and wider, allowing more cars to wait simultaneously.
- Traffic from Dronten to Harderwijk: the double left-turn waiting lane will be extended, which also reduces traffic jams.
Weekend closure in June
From Friday, June 12, 9:00 PM until Monday, June 15, 6:00 AM, the intersection will be completely closed. Traffic towards Harderwijk and between Dronten and Zeewolde will not be able to use this intersection. Detours will be set up.
Schedule
- Monday, February 2: raising the ground (road remains open, disruptions and speed restrictions)
- From February to May: soil consolidation with disruptions for traffic from Zeewolde to Harderwijk
- From May 26 to June 12, 2026: work on exits towards Harderwijk with disruptions at the entire intersection
For the most current information about the work, visit the webpage www.flevoland.nl/Gooiseweg.