From Monday, August 18, various works will be carried out on and around the Herbert H. Dowweg (N252) near Terneuzen. The work will last until Monday, September 15, 2025.
What exactly will happen?
The Province of Zeeland will construct a new roundabout at the Maintenance Value park in Terneuzen and will carry out asphalt maintenance on the Herbert H. Dowweg (N252). Water Board Scheldestromen will perform asphalt maintenance for the main access gate of Dow (gate 1). ProRail will start replacing the railway tracks at the railway crossing in the Herbert H. Dowweg. The N.V. Westerscheldetunnel will re-asphalt the access and exit roads from the Westerscheldetunnelweg to the Herbert H. Dowweg.
Detour routes
The work will cause necessary inconvenience. The work will be carried out in several phases, with different detour routes for each phase. The detour routes will be indicated with yellow signs. Also, during a large part of the work, the last exit for the Westerscheldetunnel will be closed. The detours per phase can be found at Melvin.
Overview of the work
- Work on the bike path Innovatieweg. From Monday, August 18, 07:00 to Saturday, August 30, 18:00: Melvin - Situation details M433047.
- Work on the roundabout Innovatieweg. From Monday, August 18, 07:00 to Saturday, August 23, 05:00: Melvin - Situation details M293747.
- Combined work on the roundabout Innovatieweg and railway crossing. From Saturday, August 23, 05:00 to Sunday, August 24, 23:00: Melvin - Situation details M469075.
- Work on the roundabout Innovatieweg. From Sunday, August 24, 23:00 to Friday, September 5, 19:00: Melvin - Situation details M469191.
- Complete weekend closure of the roundabout Innovatieweg. From Friday, September 5, 19:00 to Monday, September 8, 05:00: Melvin - Situation details M433243.
- Asphalt maintenance N252 east side. From Monday, September 8 to Friday, September 12 between 19:00 and 05:00: Melvin - Situation details M293454.
- Asphalt maintenance N252 west side. From Friday, September 12, 19:00 to Monday, September 15, 05:00: Melvin - Situation details M293523.
Want to know more?
If you have questions about the work, you can contact Pippin Kole, the project manager of the contractor KWS, via pkole@kws.nl or 06-53333665.