This autumn, major maintenance of lock Bosscherveld has been on the agenda for some time. The planning for this is now known. Part of it will take place in the summer, and part will start this autumn. The lock will be disrupted during these periods.
Summer Disruption for Concrete Repair
To ensure that the installation of the drying equipment can happen safely and securely, it has been decided to bring the concrete repair forward. This ensures a stable start to the major maintenance.
This work will last a maximum of 6 weeks and will take place between June 2 and July 20, 2025.
Long-term Disruption This Autumn
The disruption this autumn will last a long time, as we had also announced. According to the current planning, this will take about 9 months: we will start on September 29, 2025, and expect it to last until approximately June 30, 2026.
This is not good news, we are aware of that. We have been in contact with the industry and the surrounding area about this.
More Information on the Work at Lock Bosscherveld
If you have questions regarding the above work, please contact us.