Published on: December 12, 2025, 16:06
Schijndel Lock has been available again for shipping since Friday afternoon, December 12, 2025. The damage caused by a collision at the end of November 2025 has been repaired. Over the past period, work has been done with great effort.
Maintenance and Testing of Lock
On Thursday, December 11, the operation of the lock was extensively tested. Among other things, the extensive 3D scan showed that the doors were not damaged. The damaged parts, such as the pedestals on which the motors stood, were replaced.
In addition, the time for the necessary repairs was also used to carry out non-essential maintenance, such as cleaning the doors. On the morning of Friday, December 12, the final procedures were completed after which shipping can use the lock again.