March 2 - March 15: closure of Nittersweg and Reitdiep Bridge
From March 2 to March 15, Nittersweg (N388) will be closed from the Reitdiep Bridge to the intersection with S.H. Woldringhstraat. During this two-week closure, the contractor will install a new bicycle bridge over the Reitdiep, perform major maintenance on the N388, remove sheet piles, and refurbish the existing Reitdiep Bridge. Zoutkamp will be accessible from the north side (Ulrum/Lauwersoog) and S.H. Woldringhstraat during this period.
March 16 - April 6: partial lane closure Nittersweg, first part of Sluisweg fully closed
From March 16 to April 6, one lane of Nittersweg (N388) will be closed. The first part of Sluisweg will also be fully closed. Over three weeks, the contractor will carry out various works on the road, including drainage, gutter construction, and paving. All traffic can pass the Reitdiep Bridge.
April 7 - April 14: closure of Nittersweg and Reitdiep Bridge
From April 7, Nittersweg (N388) and the Reitdiep Bridge will be fully closed again. This is necessary to apply the asphalt layer and the coating & markings. Zoutkamp will be accessible from the north side (Ulrum/Lauwersoog) and S.H. Woldringhstraat during this period. Cyclists and pedestrians can still cross the bridge.
From April 15 to April 19, there will be no closures. Some minor works will take place during this period.
April 20 - May 3: closure of S.H. Woldringhstraat
From April 20 to May 3, S.H. Woldringhstraat will be closed to all traffic. Access to Zoutkamp is via Sluisweg. The main road in Zoutkamp (N388, Reitdiep Bridge, and Hunsingobrug) will be open to all traffic.
May 4 - May 13: major maintenance on N388 and Hunsingobrug
From May 4 to May 13, the N388 will be closed near the Hunsingobrug and S.H. Woldringhstraat. The Hunsingobrug will be repaired and the N388 will undergo major maintenance.
Zoutkamp will be accessible from the south side (Grijpskerk) and Sluisweg. Cyclists and pedestrians can temporarily use the new footbridge over the Hunsingosluis.
During the works, buses will run on their normal schedule. The route will be slightly shortened, ending at the bus stop on Panserweg.
Detours during closures
During full closures, traffic will be diverted via the available route around Zoutkamp. Because only a limited detour route is available, closures cause significant extra travel time. The advice is to follow the detour signs and turn off navigation systems.
Weekly consultation hour
Residents and entrepreneurs can ask questions during the weekly consultation hour on Friday mornings from 9:00 to 12:00. The information center is located in the parking lot at the ice rink, at Panserweg 8 and 9 in Zoutkamp.
More information
See all information about closures and detours on our website.